Ground Lease Model 2 South Yarra

Trackworks
  • >6,600total workhours
  • >6.,000M3concrete poured
  • 1,930M340MPa
  • 4,090M365MPa
  • 69M380MPa
  • 501foundation piles
  • 331900mm dia piles
  • 1951200mm dia piles
  • 20crane piles
  • 5sacrificial test piles
  • CFA Foundation Piles
  • Concrete Supply & Placement
  • Temporary Works Engineering
  • Quality Assurance
  • Total 501 foundation piles, including more 6,000m3 of concrete
  • Drilling depths ranged between 11-30 metres
  • Five sacrificial piles installed, with a total of 22 test piles verified to loads between 5,820kN and 7,606kN
  • Concurrent drilling activity within close proximity of each other – requiring careful planning, sequencing and coordination